The supply includes the provision of services commissioning of a command system, installed in substation, 220/132/33 kV of Njiro.
The supply includes the provision of research services, configuration, parameterization, testing and commissioning of two substations in Paraguay with voltage levels of 230/ 24.3kV, substation consisting of a command and control system EFACEC, and protection relays Schweitzer SEL, in the 24.3kV existing will be implemented one Efacec command and control system for integration into HMI substation.
The scope of supply included the provision of configuration, parameterization, testing and commissioning services for 3 RTUs, composed of a capacitor bank, transformer reducers, and several outputs, installed in existing substations.